Saturday, June 18, 2005

House Renovation week 10


house reno week 10 - 1
Originally uploaded by NTRMonjoy.
The bedroom floor needs a bit of levelling!

Week 10 of the renovation and extension. Piers have been dug and filled in the old house, 2m deep. Piers have also been dug and filled for the new section of the house, 3m deep, much deeper and they would have been into the Aquifer that provides our bore water. (only 4 m deep round here). Still the engineer specified it so that's what Steve (our builder) has done, it was all inspected, approved and completed in a day.

[joe]

2 Comments:

At 7:23 pm, June 18, 2005, Anonymous Anonymous said...

What , Tony you neigbour did not make an appearance today at the house.

I suppose we can be thankfull for small blessings hey !! LOL

 
At 7:50 pm, June 18, 2005, Blogger Dino & Joe said...

no such luck, the curtains were twitching within a minute of our arrival. we got him with the video camera tho'

 